Callaway is interested in if any plants allow Fin type tool pouch work to be conducted in the RCA without RP assessing the jobs?


The process currently:
Fin Supervisor calls to RP and requests that an RWP be assigned to a specific job.
RP looks at job and assigns an RWP to the job in our work control program.
Fin maintenance reports to the access point to sign into the RCA and work the job with the assigned RWP.

Our FIN group would like to not call RP to get the RWP assigned and just use the generic FIN RWP and be responsible for knowing the conditions at the work site and the RWP requirements.

Any information that you have on this would be appreciated.

Thanks,

Aaron Enloe
Supervising Health Physicist
Radiation Protection
Callaway Nuclear Station
573-592-9286

This communication and any attachments may be privileged and/or confidential and protected from disclosure, and are otherwise the exclusive property of Ameren Corporation and its affiliates (Ameren) or the intended recipient. If you are not the intended recipient, you are hereby notified that any dissemination, distribution or copying of this communication is strictly prohibited. Note that any views or opinions presented in this message do not necessarily represent those of Ameren. All e-mails are subject to Ameren policies. If you have received this in error, please notify the sender immediately by replying to the message and deleting the material from any computer.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20210825/fee8707b/attachment-0001.html>


More information about the Global mailing list