R.VanHoorebeck at dominionenergy.com R.VanHoorebeck at dominionenergy.com
Mon Aug 30 14:35:10 EDT 2021


Was wondering how you all coordinate scaffold builds and removals with regard to minimizing dose to crews.  At Surry, all scaffold build crews are briefed by ALARA to include photos of area and dose rates.  General recommendations on limiting crew size in higher dose areas...etc. We do not have a dedicated tech to provide coverage.  The rover provides support for the scaffold crews.

Do you have a dedicated RP Tech to support scaffold work during outages?  If so, do they manage all the briefings as well?  Also, if you have a dedicated tech, does it reduce dose and improve productivity?

Thanks!

Doug VanHoorebeck
ALARA Supervisor
Surry Power Station
W: 757-365-2642
C: 757-617-4191
r.vanhoorebeck at dominionenergy.com<mailto:r.vanhoorebeck at dominionenergy.com>

CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect.  The information is intended solely for the individual or entity named above and access by anyone else is unauthorized.  If you are not the intended recipient, any disclosure, copying, distribution, or use of the contents of this information is prohibited and may be unlawful.  If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20210830/dddde5b8/attachment-0001.html>


More information about the Global mailing list