[Global] Reactor Disassembly
Ray Vannoy
arvannoy at aep.com
Wed Jan 8 08:42:16 EST 2020
Happy New Year to All
Our Reactor Services Group is asking for us to remove the reactor head with the studs left in the head after detention is complete.
They then want to install the stud hole plugs with the top part of the Upper Internals exposed.
At the end of refueling it is reversed, set the internals, remove and clean stud holes and plugs.
Our Effective Dose Rates (EDR) with the top plate of the internal exposed is 300 mr/hr.
It generally takes us 20 person hours to install plugs and 30 person hours to remove and clean holes.
Our first answer is no.
So what I am asking do any PWR's perform reactor disassembly this way? Pro/Cons
Does any PWR's use stud covers instead of stud hole plugs?
Thank You
Ray Vannoy
RP/ALARA
Cook Plant Employees Club Representative
Donald C. Cook Nuclear Plant
1 Cook Place
Bridgman. Mi. 49106
269-465-5901 ext. 2037
Email; arvannoy at aep.com<mailto:arvannoy at aep.com>
[aep for email]
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20200108/dbf63fe6/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 3266 bytes
Desc: image001.jpg
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20200108/dbf63fe6/attachment.jpg>
More information about the Global
mailing list