I've been tasked with hitting you all up for suggestions to resolve a situation we're facing in an upcoming outage.

We have to do extensive weld pad buildups under 2 root valves (per Hot Leg) which were installed with socket welds. They read up to 4.3 R/hr contact over 220 mR/hr @30 cm. The welders will be approx. 2 ft below them. I have specialty shielding available that I anticipate will give me an about 20 mR/hr G/A in the work area. Outage management is reluctant to cut these valves off, decon, and replace them due to cost and schedule considerations. I can't increase shielding without creating a weld machine interference. I considered flushing but have no way to come from tubing through the valve into piping and create enough pressure to flush 3 socket welds back into the Hot Leg.

Hit it hive mind! And thanks in advance.
[cid:image005.jpg at 01D79DB4.BE66C800]    [Diagram  Description automatically generated]


Bill Meldrum
Oconee Nuclear Station
RP/ALARA
x 3204
864-873-3204<tel:864-873-3204>
Cell 803-229-2204

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20210830/9f076c11/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image005.jpg
Type: image/jpeg
Size: 20647 bytes
Desc: image005.jpg
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20210830/9f076c11/attachment-0001.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image006.png
Type: image/png
Size: 89065 bytes
Desc: image006.png
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20210830/9f076c11/attachment-0001.png>


More information about the Global mailing list