[Global] OPEX Request; Holtec MPC Port Plug replacement

Renn Guy guy.renn at edf-energy.com
Wed Jun 25 08:10:20 EDT 2025


Sizewell B (Westinghouse 4-Loop second generation) is preparing to replace a Holtec Multi-Purpose Cannister port plug due to an emergent helium leak during cask processing.
Holtec say that they have carried out this repair at other nuclear sites. We would be grateful for any feedback on the task, particularly the RP controls applied and radiological conditions encountered during the work. This will help us to validate our proposed controls.

Thanks in advance for any information.

Guy Renn
Radiation Protection Adviser
Sizewell B NPP

T: +44 (0)1728 653 950 (Ext)
T: 718 3950 (Int)

Sizewell B Power Station
Leiston, Suffolk, IP16 4UR
United Kingdom
 [cid:image001.png at 01DBE5D2.7CF3D8D0]

edfenergy.com<http://www.edfenergy.com/>

Please consider the environment before printing this email

This e-mail, and any attachments, is confidential and for the use of the addressee only. If you are not the intended recipient, please telephone +44 (0) 1355 846000. We do not accept legal responsibility for this e-mail or any viruses. All e-mails sent and received by us are monitored. Contracts cannot be concluded with us by e-mail.
This message has been sent from EDF Energy Nuclear Generation Ltd, a company registered in England and Wales No. 03076445, with registered office at Javelin House, Building 1420 Charlton Court, Gloucester Business Park, Gloucester GL3 4AE. 
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20250625/10193fa3/attachment-0001.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 8156 bytes
Desc: image001.png
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20250625/10193fa3/attachment-0001.png>


More information about the Global mailing list