[Global] Beaver Valley Reactor Cavity Decon Benchmark

Kennedy, Kyle Anthony kakennedy at tva.gov
Wed Mar 2 14:18:06 EST 2022


See below/attached

From: Global <global-bounces at list.rpalara.org> On Behalf Of Fontaine, Jeffrey W
Sent: Wednesday, March 2, 2022 10:40 AM
To: global at list.rpalara.org
Cc: Ruby, Robby P <rpruby at energyharbor.com>; Coradi, David V <dcoradi at energyharbor.com>
Subject: [Global] Beaver Valley Reactor Cavity Decon Benchmark

This is an EXTERNAL EMAIL from outside TVA. THINK BEFORE you CLICK links or OPEN attachments. If suspicious, please click the “Report Phishing” button located on the Outlook Toolbar at the top of your screen.

Beaver Valley is performing a benchmark of Reactor Cavity Decon Practices.  Your participation is appreciated.

Power Station   WBN      PWR    X     BWR____
Contact  Phone #    423-365-8022
Email Address kakennedy at tva.gov

  1.  Do you perform Reactor Cavity Decon with House Personnel? Contractors assigned to plant laborer group  If not, who do you contract with to perform the work?
  2.  Do you hydrolase the walls or cavity floor    pressure wash (with heated pressure washer) and squeegie
If you do, what areas do you hydrolase? Briefly describe.__
Upper Cavity: Floor, rust ring, & as high as can be reached up the walls without spraying upwards. Second jump (post head set) alconox walls/floor, wipe walls (wet, dry, wet), mop floor (wet/dry/wet).
Lower Cavity: pressure wash & squeegee same as upper cavity then spray alconox. Buff floor/doodle bug walls & stand legs, pressure wash & squeegee again.
            All water/crud gets washed into transfer canal (~4’ below equipment pit floor)
To what contamination levels do you strive to achieve? Upper Cavity: <50k, Lower Cavity: <100k

  1.  What deconning agents if any, do you use on the walls and /or floor? Alconox & spray n wipe
  2.  Which types of materials/chemicals do you decon with? __X__mops
___X_____rags ___X____ Scrub Pads__________ Hydrogen Peroxide
____X____high pressure washing _____FLOOR BUFFER______other, describe

  1.  Do you use any robotics to perform decon of the cavity?   NONE
If so, what type

  1.  Generally, how long does it take to decon the cavity? Time from initial RP survey to the time in which refueling re-enters the cavity ~15 minutes for initial washdown, 60-120 minutes for second cavity decon
  2.  Are other groups working in the cavity in parallel with the decon crew?  None
If so, briefly describe

  1.  Estimate the amount of exposure in mRem that it takes to decon the Reactor Cavity?
___X____100-500 _____500-750 _____>750 mRem

  1.  What recent changes have you made to decrease the time required to decon the cavity and/or reduce the exposure that it takes to achieve your decon goal?
  2.  Do you have a detailed procedure for this activity? If so, would you consider providing a copy for us to review?  We did have a procedure, but it was deleted in order to allow for deviations (not our choice). So we have a job aide/decon script that we wrote (attached).

Please include Rob Ruby (Beaver Valley Power Station) in your response. Email: rpruby at energyharbor.com<mailto:rpruby at energyharbor.com>

Jeffrey Fontaine
ALARA Supervisor
Beaver Valley Power Station
Email  fontainej at energyharbor.com<mailto:fontainej at firstenergycorp.com>
Desk Phone 724-682-5120
Cell Phone 724-462-3423


Electronic Confidentiality and Privacy Notice: This e-mail, and any attachments, contains information that may be confidential, constitutes non-public information, may be protected by electronic communication privacy laws, or is a privileged communication (attorney-client or otherwise). The information contained in this message is intended only for the personal and confidential use of the recipient(s) named above. If the reader of this message is not the intended recipient or an agent responsible for delivering it to the intended recipient, you are hereby notified that you have received this document in error and that any review, use, disclosure, dissemination, distribution, or copying of this message is strictly prohibited. If you have received this communication in error, please notify the sender immediately by reply e-mail or by phone, and destroy all copies of the original message.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20220302/a2015881/attachment-0002.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: POST CORE LOAD RP PS SEQUENCE.docx
Type: application/vnd.openxmlformats-officedocument.wordprocessingml.document
Size: 16001 bytes
Desc: POST CORE LOAD RP PS SEQUENCE.docx
URL: <http://list.rpalara.org/pipermail/global_list.rpalara.org/attachments/20220302/a2015881/attachment-0002.docx>